Nintendo USA Project

Machine Rebuild Roadmap • Štěnovice

Milestone 1: Box Handling

May (CW 18) - Late May
In Progress

Rebuilding the line for box flow using 3D printed prototype parts.

Box Opening & Carousel setup
Box Placement & Main Track adjustments
Box Closing & Lifting Arm integration
90-degree Rotation unit configuration

Milestone 2: Material Insertion

June
Upcoming

Adjusting the line for media and document insertion using 3D printed parts.

Inlay Sheet Insertion station setup
Booklet Insertion calibration
Game Card Insertion fine-tuning

Milestone 3: Robot & Magazine

July
Upcoming

Integration of specialized Nintendo card handling hardware.

Robot base construction
Magazine system & Tray elevator build
Safety systems & Electrical wiring
Full machine guarding

Milestone 4: Finalization

August (until Aug 21)
Upcoming

Transition to final hardware and quality assurance.

Replacement with final metal components
Live production testing (Ostré zakázky)
Final quality control sign-off

Final Logistics & Export

Preparation for overseas shipment to the USA.

Line Disassembly
Aug 22 – Aug 24 • Careful dismantling for transport (3 days)
Packing & Loading
Aug 25 – Aug 27 • Container loading for sea shipment (3 days)
Shipment Departure
August 27 • Final departure for USA
Departure Date AUG 27 Milestone Confirmed