Machine Rebuild Roadmap • Štěnovice
May (CW 18) - Late May
Rebuilding the line for box flow using 3D printed prototype parts.
June
Adjusting the line for media and document insertion using 3D printed parts.
July
Integration of specialized Nintendo card handling hardware.
August (until Aug 21)
Transition to final hardware and quality assurance.
Continuous creation of user manuals, safety protocols, and technical specifications for the new machine setup.
Porting logic and hardware for non-standard components like the new Control Panel to ensure full compatibility.